Monday, July 29, 2013
07-29-2013 Day 107
Called Bill @ 8 am left VM, Called Matt and left a voice mail. He called me and left a voice mail, and I called him right back. We were finally able to talk!. He expressed how upset he was with Bill , and that this should have never gone this far. He is pulling Bill from this "Service" issue, and putting Antwan (a different project manager) on it. I texted pictures of the product Bill left on site. I received a call from Antwan and went over my expectations: 1) a single lite coat of the cleaner, spray it off and allow it to dry for 24 hours. If we think it needs more he will need to come back and do another coat. 2) When the pavers look good, they can then replace the bad ones and re-apply the sand 3) If touch ups are needed spray again 4) fix the steps that are not glued down and are moving, and the fire pit pavers that were not locked down.
Friday, July 26, 2013
07-26-2013 Day 106
Left 2 Voicemails for Bill and Matt Asking for a status, No call back I expresses my concerns of how now I am being ignored by both my contacts at Builders Unlimited
Thursday, July 25, 2013
Wednesday, July 24, 2013
Tuesday, July 23, 2013
Monday, July 22, 2013
07-22-2013 Day 102
Bill was supposed to show up today to spray down the patio, so I again stayed home from work to supervise the activities. He was a no call no show. Left 2 voice mails, received no response.
Thursday, July 18, 2013
07-18-2013 Day 100
Talked with Bill and he has the product, we scheduled the Following Monday to do the whole patio.
Tuesday, July 16, 2013
07-16-2013 Day 98
Called Bill back asking for a status, and was told that the product was being delivered from Oberfields' Delaware Location
Monday, July 15, 2013
07-15-2013 Day 97
Called Bill Asking for a plan / schedule, he said that he needed to get the product from Oberfields.
Thursday, July 11, 2013
07-11-2013 Day 95
Bill came onsite to spot test the new chemicals. One large area Bill sprayed 3 times and let it sit. I had Bill test one paver by spraying it one time and letting sit for 5 minutes, then washing it off. This area looked the best. Bill was only here in the morning for a hour or so. I told him I would update him with the results by the end of the day. I did this and sent him txt pictures showing the difference between the two methods of spraying. He told me that he would get more chemical ASAP to finish up the job.
View from second story window where you can see the bright tan treated areas. |
Up-close of the spot treated area |
Wednesday, July 10, 2013
07-10-2013 Day 94
I had to call Matt and ask him to have Bill call me. I again expressed frustration as to how I have to call the owner to get a call back from the project manager. By the end of the day Bill called and he agreed to come out the next
Tuesday, July 9, 2013
07-09-2013 Day 93
I texted Bill asking him when he was coming out to spot test the chemical that Lou from Oberfields advised him to use on the patio. No response
Subscribe to: